Scaffold & Sidewalk Shed Reforms in NYC: What Changed and How to Comply
- Admin N

- Nov 8, 2025
- 2 min read

New York City enacted a package of laws in 2025 to reduce long-standing sidewalk sheds, improve lighting and design, and push façade repairs forward faster. The reforms were passed by the City Council in March and signed by the Mayor on April 17, 2025.
The Headliners
12-ft minimum clear height (Local Law 47 of 2025).
Sidewalk sheds filed on or after August 15, 2025 must provide 12 feet of clear height (previously 8 ft). DOB’s service notice clarifies scope, exceptions (e.g., where 12 ft would interfere with required light/air), and that filings submitted before 8/15/25 are not forced to retrofit.
Shorter permit duration for façade-repair sheds.
For sheds associated with façade work, permits are now three months instead of a year, with progress required for renewals and increasing penalties for delays. (Council legislation package; DOB enforcement under “Get Sheds Down”.)
Brighter, better lighting (LED).
New rules require LED lighting and more foot-candles under sheds, with shielding near residential windows to prevent glare—part of the reform package signed in April 2025.
Design & aesthetics upgrades.
The laws expand allowable shed colors and direct DOB to produce a design study and recommendations by September 30, 2025, to make sheds less intrusive while maintaining safety; those recommendations inform future code updates.
What This Means for Owners, Contractors, and CM/GCs
Plan for 12 ft on new filings (unless a documented exception applies). Coordinate early with designers to meet height, lighting, and egress requirements.
Expect more frequent renewals for façade-related sheds. Build progress checkpoints (scope completed, inspections scheduled, filed permits) into your schedule to avoid escalating fines.
Upgrade lighting specs to LED and verify shielding where sheds run alongside residential windows. Include this in procurement and close-out checklists.
Watch for DOB’s design guidance. When the design study and any resulting standards are published, align your shed vendors and site templates.
What Did Not Change
These NYC reforms do not alter OSHA/NYS training hour requirements for workers assembling or using scaffolds. Your scaffold safety training content (erection/inspection, load capacity, fall protection, weather, communication) remains the same; the reforms primarily target public-way sheds management, duration, lighting, and design, not worker curriculum. (See Mayor’s and Council releases; no DOB notice indicates training-hour changes.)
Official Sources (for your “References” section)
NYC DOB Service Notice: “Increased Ceiling Heights for Sidewalk Sheds” (LL47; effective Aug 15, 2025).
NYC Council press release: “Votes to Reform Scaffolding and Sidewalk Shed Rules” (package passage, March 26, 2025).
NYC Council release on bill signing (Apr 17, 2025).
Office of the Mayor press release: “Mayor Adams Signs Historic Legislation to ‘Get Sheds Down’…” (Apr 17, 2025).
Local Law 47 of 2025 (DOB PDF; design study & timeline toward new standards).
DOB “Building News” updates for Get Sheds Down implementation.